A hot week of construction! 

  • The blue house next to the Board of Education has been demolished and the area is being cleaned up to prepare for a parking/trailer area during construction.

 

  • The gym behind the MIddle School is still being demolished.  YOu can actually see inside the gym now.

 

  • The modular work continues.  The technology wiring will start this week.

 

  • We anticipate moving furniture and materials into the modulars around August 1, if all continues to go according to the schedule.