Construction Update – June 21, 2013

WMS Construction Blog

It has been a busy week on the Middle School project…..

  • All contents in the school building were put in storage or sold.  We had a very successful garage sale thanks to the many volunteers and maintenance staff who helped.  We sold or “repurposed” over 80% of the items!  We helped out some schools, non-profits and an assisted living center with our furniture and materials.  Items from the sale helped schools in Winton Woods, Africa and even Guatemala! Thanks to all of the volunteers who gave of their time on Friday and Saturday to make this event a success.
  • We are now doing the asbestos abatement in the band room and gym areas.  When the abatement is finished, we will start the demolition of those build areas.
  • The demolition company will be using dust control when tearing down the building.  The dust control involves wetting down the areas when it…